Mounting the Cantilever

The design required a staged construction and collaboration of the engineers and construction managers. The roof slabs were installed first for support, extending back all the way to the level 4 stairs. Then allowing for a 25m drop (subsequently measured by geomatics) in the horizontal beams as the concrete slabs for each floor were added.

The diagonal support can be seen behind the glass on the east and west sides.

The anchor point to the building.
The anchor point to the building.
Structural steel
The structural steel frame.
Temporary padfootings
The square holes in the ground are temporary padfootings which support the temporary columns whilst the cantilever was being constructed. The load on each diagonal steel member is 150 tonnes.
The cantilever has had the temporary columns removed.
The cantilever after the temporary columns are removed.

Read next about constructing the Cantilever.